Project Management MCQ Quiz - Objective Question with Answer for Project Management - Download Free PDF

Last updated on Apr 12, 2023

Latest Project Management MCQ Objective Questions

Project Management Question 1:

What are the characteristics of job shop production ?

A. Different product types are produced

B. Very large quantities are produced

C. Single type of product is produced

D. Low quantities of product are produced

  1. A and B
  2. C and D
  3. B and C
  4. A and D

Answer (Detailed Solution Below)

Option 4 : A and D

Project Management Question 1 Detailed Solution

Explanation:

Job – shop production

  • Job – shop production is characterized by the manufacturing of a large variety of products in small quantities that are designed and produced as per specifications are given by customers
  • The main feature of this production system is that it is highly flexible
  • A shop – shop comprises general-purpose machines arranged in different departments
  • Example – Manufacture of aeroplanes and oil field equipment, machine tools, giant hydro turbine, rolling mills, and other heavy equipment

 

Batch production

  • Batch production is a type of production in which the job passes through the functional departments in batches and each batch may have a different routing
  • Batch production is characterized by the manufacture and stocking of a limited number of products at regular intervals, awaiting sales
  • Example – Machine tools, pumps, compressors, stationary IC engines, etc.

 

Mass production

  • In mass production, the same type of product is manufactured to meet the continuous demand of the product
  • Manufacturing of discrete components or assemblies in a very large volume is called mass production
  • Machines are arranged in a line according to the sequence of operations on the product
  • Example – Nuts, bolts, screws, washers, pencils, matches, engine blocks, bicycles, electric motors, sewing machines, tractors, etc.

 

F1 S.S. N.J 19.07.19 D 2

Project Management Question 2:

Zaire proposed "Building blocks of TQM" in which year ?

  1. 1987
  2. 1991
  3. 1973
  4. 1981

Answer (Detailed Solution Below)

Option 2 : 1991

Project Management Question 2 Detailed Solution

Explanation:

TQM:

  • Total Quality Management (TQM) is a management approach that originated in the 1950s and has steadily become more popular since the early 1980s.
  • Total quality is a description of the culture, attitude, and organization of a company that strives to provide customers with products and services that satisfy their needs.
  • The culture requires quality in all aspects of the company’s operations, with processes being done right the first time and defects and waste eradicated from operations.
  • The "Building blocks of TQM" were specifically proposed by Joseph Juran in his book "Juran on Quality Improvement" in the year 1989.
  • According to Zaire and Simintirais (1991) TQM  is a combination of socio technical process towards doing the right things externally, every thing right (internally), the first time and all the time with economic viability at each stage of each process

To be successfully implement TQM, an organization must concentrate on the eight building blocks are:

  1. Ethics
  2. Integrity
  3. Trust
  4. Training
  5. Teamwork
  6. Leadership
  7. Recognition
  8. Communication

Project Management Question 3:

The earliest method used for planning of projects was

  1. CPM
  2. PERT
  3. Bar chart
  4. Milestone chart

Answer (Detailed Solution Below)

Option 3 : Bar chart

Project Management Question 3 Detailed Solution

Explanation:

  • The first method invented for planning projects was the bar chart method which was introduced by Henry Gantt around the year 1900 A.D.
  • Bar chart is therefore also referred to as Gantt Chart. A bar chart is a graphical representation of activity v/s time where the horizontal axis represents time duration and the vertical axis represents activities.

Bar chart (Gantt chart):

(i) It is a pictorial chart.

(ii) It has two coordinate axes, the horizontal line (coordinate) represents the elapsed time and the vertical coordinate represents the job or activity to be performed.

(iii) The beginning and end of each bar represent starting and finishing times of a particular activity respectively.

(iv) The length of the bar shows the time required for completion.

 Additional InformationLimitation of a bar chart:

(i) Lack of degree of detail.

(ii) A bar chart does not show the progress of work and hence it can not be used as a control device.

(iii) A bar chart is unable to depict the interdependencies of various activities clearly.

(iv) No provision to account for time uncertainties.

(v) Bar chart can not distinguish between critical and non-critical activities and hence resource smoothening and resource-leveling can not be done.

Project Management Question 4:

A public limited company has 9,00,000 shares outstanding at current market price of Rs. 130 per share. The company needs Rs. 2.25 crores to finance its proposed new project. The board of the company has decided to issue rights shares to raise the required money at Rs. 75 per share (as subscription price) to ensure that the rights issue is fully subscribed. How many rights are required to purchase a new share ?

  1. One right
  2. Two rights
  3. Three rights
  4. Four rights

Answer (Detailed Solution Below)

Option 3 : Three rights

Project Management Question 4 Detailed Solution

The correct answer is Three rights

Key Points

  •  Information Given in Statement:
  •     Number of shares = 900,000
  •     Required Finance = Rupees 2.25 Crores
    •  i.e. 2,25,00,000
  •     Current M.P (Market Price) = Rupees 130 per share
  • Subscription price = Rupees 75 per share

Computation :

  • Firstly, we have to find out the Market value of company:
    •       = 9,00,000 * 130
    •       = 1,17,000,000

 

  • A company needs to issue shares, for Rupees 2,25,00,000 with Subscription price of Rupees 75:
    •       =  2,25,00,000 / 75
    •       = 3,00,000 shares

 

  • Now, with the help of given information we can easily find out the rights that are required to purchase a new share.
    •        = 9,00,000 / 3,00,000
    •        = 3 Rights

 

  • So, three rights are needed to purchase a new share.

 

Hence, the correct answer is Three rights.     

Project Management Question 5:

The following statements relate to project network. Choose the correct code for the statements being correct or incorrect.

Statement I: An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.

Statement II : The activities in a critical path can be preponed or postponed.

  1. Both the statements I and II are correct.
  2. Both the statements I and II are incorrect.
  3. Statement II is correct, but I is incorrect.
  4. Statement I is correct, but II is incorrect.

Answer (Detailed Solution Below)

Option 2 : Both the statements I and II are incorrect.

Project Management Question 5 Detailed Solution

The correct answer is (2) Both the statements I and II are incorrect.

Important Points 

  • Each activity in a critical path method is represented by a single network arrow. As a result, no single activity can have more than one representation in the network.
  • Activities can be classified as either critical or non-critical. While each non-essential activity will have some comfort time to either delay or prepone its starting time from the original starting time, no essential activity will have any cushion time to do either.

 

Hence, both the statements are incorrect. 

 

Top Project Management MCQ Objective Questions

Planning is often called the primary management function because it:

  1. Creates the vision for the organizational members
  2. Sets the tone for the organizational culture
  3. Establishes the basis for all the other functions
  4. Offers some basis for future decision making

Answer (Detailed Solution Below)

Option 3 : Establishes the basis for all the other functions

Project Management Question 6 Detailed Solution

Download Solution PDF

The correct answer is Establishes the basis for all the other functions.

  • Planning is often called the primary management function because it establishes the basis for all the other functions.

Key Points

  • The management process consists of four primary functions that managers must perform:
    • planning
    • organizing
    • leading
    • controlling
  • Planning is often called the primary management function:
    • Planning means defining performance goals for the organization and determining what actions and resources are needed to achieve the goals.
    • Through planning, management defines what the future of the organization should be and how to get there.
    • It establishes the basis for all the other functions.
    • A strategic plan bridges the gap between what an organization is and what it will become.
    • A tactical plan defines what has to be done, who will do it, and the resources needed to do it.

Crashing is

  1. Abandoning the project
  2. Completing the project with all possible haste
  3. Reduction of duration for a few of the activities
  4. Reducing the cost of the project with all needful modifications

Answer (Detailed Solution Below)

Option 3 : Reduction of duration for a few of the activities

Project Management Question 7 Detailed Solution

Download Solution PDF

Explanation:

Crashing is the method for shortening the project duration by reducing the time of one or more critical activities to less than their normal time. In crashing if cost increases then time decreases.

F1 S.C 29.7.20 Pallavi  2

The application of Special purpose material handling equipment is:

  1. Both 'Process layout' and ' Line layout'
  2. Process layout
  3. Line layout
  4. None of these

Answer (Detailed Solution Below)

Option 3 : Line layout

Project Management Question 8 Detailed Solution

Download Solution PDF

The special-purpose material handling equipment is used in the line layout. Line layout is also known as product layout.

Process Layout:

The process layout is recommended for batch production. All machines performing a similar type of operation are grouped at one location in the process layout e.g., all lathes, milling machines, etc. are grouped in the shop will be clustered in like groups.

Process layout is normally used when the production volume is not sufficient to justify a product layout.

Product Layout:

It is also known as line layout. In implies that various operations on raw material are performed in a sequence and the machines are placed along the product flow line i.e. machines are arranged in the sequence in which the raw material will be operated upon.

This type of layout is preferred for continuous production i.e. involving a continuous flow of in-process material towards the finished product stage.

RRB JE ME 40 14Q IM Part 3 Hindi - Final Diagrams Deepak images Q5

The market price per share of a company is Rs. 125. The dividend per share (DPS) is Rs 12 and DPS is expected to grow at a constant rate of 8% per annum. The cost of the equity capital to company will be

  1. 17.6%
  2. 15.4%
  3. 13.2%
  4. 11.8%

Answer (Detailed Solution Below)

Option 1 : 17.6%

Project Management Question 9 Detailed Solution

Download Solution PDF

Concept:

\(Cost\;of\;equity = \frac{{DP}}{{MPS}} + r\)

Calculation:

Given:

Market price per share = Rs 125, Dividend per share = Rs 12, Rate = 8 % = 0.08

Now,

\(Cost\;of\;equity = \frac{{DP}}{{MPS}} + r\)

\(\therefore Cost\;of\;equity = \frac{{12}}{{125}} + 0.08\)

Cost of equity = 0.096 + 0.08 = 0.176

Thus, the cost of equity = 17.6%

With reference to problem solving, fixation refers to 

  1. Focused approach to problem solving 
  2. Planned approach to problem solving 
  3. Inability to see a problem from a fresh perspective
  4. An ability to comprehend the goals to be achieved

Answer (Detailed Solution Below)

Option 3 : Inability to see a problem from a fresh perspective

Project Management Question 10 Detailed Solution

Download Solution PDF

Problem-solving is the act of defining a problem; determining the cause of the problem; identifying, prioritizing, and selecting alternatives for a solution; and implementing a solution.

There are 4 steps to solve the problem:

Step 1: Understand the problem.

Step 2: Devise a plan (translate).

Step 3: Carry out the plan (solve).

Step 4: Look back (check and interpret).

Fixation - Inability to see a problem from a fresh perspective. This impedes problem-solving, Two examples of fixation are mental set and functional fixedness.

CPM method of network analysis is

1. Ideally suited for linearly extending works

2. Meant essentially for research and development activities.

3. Activity-oriented

4. Used for planning, scheduling and controlling purposes

  1. 1 and 2 only
  2. 2 and 3 only
  3. 3 and 4 only
  4. 1 and 4 only 

Answer (Detailed Solution Below)

Option 3 : 3 and 4 only

Project Management Question 11 Detailed Solution

Download Solution PDF

Explanation:

  • Critical Path Method (CPM) have been used for planning scheduling and controlling in the construction project management.
  • It is activity oriented method.

 

 

CPM

PERT

I.

Critical path method

Programme valuation and review technique

II.

Deterministic

Probabilistic

III.

Control time and cost

Control only time

IV.

Activity oriented

Event oriented

V.

One time estimate

Three time estimate

VI.

Use-Non Research

Research

 

Which one of the following schedules shows the specific activities necessary to complete an activity or work package?

  1. Project schedule
  2. Master schedule
  3. Task schedule
  4. Internal schedule

Answer (Detailed Solution Below)

Option 3 : Task schedule

Project Management Question 12 Detailed Solution

Download Solution PDF

Explanation:

Work break down structure

Work break down (WBD) defines each deliverable and the decomposition of the deliverable into work packages.

Plan—Program—Project—Sub-project—Activity—Work—Task

  • Task schedule deals with allocation of resources related to work package as well activity.
  • When the project activities have been defined, they are broken down into tasks and after time & resource allocation, task schedules are prepared which is specified activities necessary to complete a work package.

Which one of the following risks can be reduced by investing in project or acquiring other firms that have a negative correlation with the earnings of the firm?

  1. Investment risk
  2. Business risk
  3. Financial risk
  4. Portfolio risk

Answer (Detailed Solution Below)

Option 4 : Portfolio risk

Project Management Question 13 Detailed Solution

Download Solution PDF

Explanation:

  • When two variables are negatively correlated, one variable decreases as the other increases, and vice versa. Negative correlations between two investments are used in risk management to diversify, or mitigate, the risk associated with a portfolio.
  • Business risk refers to the basic viability of a business—the question of whether a company will be able to make sufficient sales and generate sufficient revenues to cover its operational expenses and turn a profit.
  • While financial risk is concerned with the costs of financing, business risk is concerned with all the other expenses a business must cover to remain operational and functioning. These expenses include salaries, production costs, facility rent, office, and administrative expenses.
  • Interest rate risk is the risk that an investment's value will change due to a change in the absolute level of interest rates, the spread between two rates, in the shape of the yield curve, or in any other interest rate relationship.
  • This type of risk affects the value of bonds more directly than stocks and is a significant risk to all bondholders. As interest rates rise, bond prices in the secondary market fall and vice versa.

During an assessment of economic viability of the project, the ratio of average annual earnings after tax to the average book investment after depreciation is called

  1. Benefit-Cost Ratio (BCR)
  2. Net Present Value (NPV)
  3. Pay-Back Period PBP)
  4. Return on Investment (ROI)

Answer (Detailed Solution Below)

Option 4 : Return on Investment (ROI)

Project Management Question 14 Detailed Solution

Download Solution PDF

Explanation:

  • Return on Investment (ROI) is a performance measure used to evaluate the efficiency of an investment or compare the efficiency of a number of different investments. (Average rate of return is also called as return on investment).
  • ROI tries to directly measure the amount of return on a particular investment, relative to the investment’s cost.
  • It calculates the profitability of the company by measuring the earnings related to the amount of capital invested.
  • To calculate ROI, the benefit (or return) of an investment is divided by the cost of the investment. The result is expressed as a percentage or a ratio.

\(Return\;on\;investment\;\left( {ROI} \right) = \frac{{{\rm{Annual\;average\;profit\;after\;tax\;}}}}{{{\rm{Average\;investment}} \times 100}}\)

Points to remember:

  1. A benefit-cost ratio (BCR) is an indicator showing the relationship between the relative costs and benefits of a proposed project, expressed in monetary or qualitative terms. If a project has a BCR greater than 1.0, the project is expected to deliver a positive net present value to a firm and its investors.
  2. Net present value (NPV) is the difference between the present value of cash inflows and the present value of cash outflows over a period of time.
  3. Payback Period (PBP) is one of the simplest capital budgeting techniques. It calculates the number of years a project takes in recovering the initial investment based on the future expected cash inflows.

What is an optimizing strategy?

  1. Strategy of choosing the best possible solution considering all parameters
  2. Strategy of choosing a compromise solution
  3. Strategy of choosing the least cost solution
  4. Strategy of choosing a solution on the basis of precedents

Answer (Detailed Solution Below)

Option 1 : Strategy of choosing the best possible solution considering all parameters

Project Management Question 15 Detailed Solution

Download Solution PDF

Explanation:

  • Finding an alternative with the most cost-effective or highest achievable performance under the given constraints, by maximizing desired factors and minimizing undesired one.
  • In comparison, maximization means trying to attain the highest or maximum result or outcome without regard to cast or expense.

F1 S.C 1.8.20 Pallavi D 2

Get Free Access Now